Serving the needs of the global Oil & Gas Industries

Taweelah Fujairah Gas Pipeline

Fabrication and installation of high-pressure piping works, site erection of piping spools, two GAS heater pipe supports, access platforms, crossovers, pipe racks, vent platform, handrails and gratings, pre-commissioning assistance and assistance with operational start up.

End Client:   Dolphin Energy

Contractor:   STG (StroyTransGaz)

Dates:   Jun 2010 to Apr 2011.

Challenges:

Working in a running plant is always a challenge.  This was only achieved by thorough co-ordination between Dolphin Energy, StroyTransGaz and our own project team. 

The other major challenge was the schedule thickness of the welds.  Welds of 64mm require specialist training, careful supervision and support for the welders undertaking the task.

 

Notes:

Dolphin Energy of Abu Dhabi operates the North field in Qutar.  The gas is brought ashore at Taweelah on the Abu Dhabi Coast.  The Taweelah - Fujairah pipeline takes the gass 244 kilometers to Fujairah on the UAE East Coast. www.dolphinenergy.com

STG (StroyTransGaz)  is involved in the engineering and construction of pipeline systems, oil and gas production facilities, underground gas storages, as well as civil and industrial structures and facilities. www.stroytransgaz.com